Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | B: 119. Manage and Administer project associated with RDC Maintenance at NPT Facilities | 10/31/2026 | ||
Obtain Permits and submit copies to BPA NEPA group | C: 165. Obtain Permits and submit copies to BPA NEPA group | 10/31/2026 | ||
Construct new east side S-channel concrete lining. | D: 61. NPTH - East S-Channel Repairs | 10/31/2026 | ||
Replace liner in NPTH fall Chinook acclimation ponds | E: 61. NPTH - Fall Chinook Acclimation Pond Liner Repair | 10/31/2026 | ||
Replace Chilled Water System | F: 61. NPTH - Replace Chilled Water System | 10/31/2026 | ||
Replace surface water cyclone seperators | G: 61. NPTH - Replace Surface Water Cyclone Separators | 10/31/2026 | ||
Replace NPTH 50hp surface water pumps (3) | H: 61. NPTH - Replace Surface Water Submersible Pumps | 10/31/2026 | ||
Replace NPTH HVAC Systems | I: 61. NPTH - HVAC Replacement | 10/31/2026 | ||
Complete NPTH Office/Residence Maintenance | J: 61. NPTH - Office/Residence Maintenance | 10/31/2026 | ||
Upgrade and replace Lukes Gulch and Cedar Flats Acclimation site alarm systems | K: 61. NPTH ALL SATELLITES - Upgrade and Replace Alarm Systems | 10/31/2026 | ||
Install 3 Phase power to Lukes Gulch Acclimation site | L: 61. LUKES GULCH - 3 Phase Power | 10/31/2026 | ||
Replace NLV park model trailer | M: 61. NORTH LAPWAI - Replace Park Model Trailer Residence | 10/31/2026 | ||
Install Shade Cloth | N: 61. SWEETWATER SPRINGS - Replace Shade Cloths | 10/31/2026 | ||
Complete Lostine Acclimation Facility Move | O: 61. LOSTINE ACCLIMATION - Facility Relocation | 10/31/2026 | ||
Produce an Annual Operation Plan | P: 174. Not required under this contract | 10/31/2026 | ||
Completed Annual Report - Not Required | Q: 132. Not required under this contract. | 10/31/2026 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Manage and Administer project associated with RDC Maintenance at NPT Facilities | |||||||
C | 165 | Obtain Permits and submit copies to BPA NEPA group | |||||||
D | 61 | NPTH - East S-Channel Repairs | 11/30/2023 | ||||||
E | 61 | NPTH - Fall Chinook Acclimation Pond Liner Repair | 11/30/2023 | ||||||
F | 61 | NPTH - Replace Chilled Water System | 02/22/2024 | ||||||
G | 61 | NPTH - Replace Surface Water Cyclone Separators | 11/30/2023 | ||||||
H | 61 | NPTH - Replace Surface Water Submersible Pumps | 11/30/2023 | ||||||
I | 61 | NPTH - HVAC Replacement | 11/30/2023 | ||||||
J | 61 | NPTH - Office/Residence Maintenance | 11/30/2023 | ||||||
K | 61 | NPTH ALL SATELLITES - Upgrade and Replace Alarm Systems | 11/30/2023 | ||||||
L | 61 | LUKES GULCH - 3 Phase Power | 11/30/2023 | ||||||
M | 61 | NORTH LAPWAI - Replace Park Model Trailer Residence | 11/30/2023 | ||||||
N | 61 | SWEETWATER SPRINGS - Replace Shade Cloths | 11/30/2023 | ||||||
O | 61 | LOSTINE ACCLIMATION - Facility Relocation | 11/30/2023 | ||||||
P | 174 | Not required under this contract | |||||||
Q | 132 | Not required under this contract. |